Two-Story Addition in Beacon, NY

This family was running out of room, and their house sits on a narrow 50-foot city lot. Building out to the side wasn't an option, so we added two stories off the back.

​

How we built it

The addition sits on concrete piers set 48 inches below grade instead of a full foundation. That meant we could frame almost the whole addition before opening the back wall of the house, so the family lived at home through the entire build.

​

We started at the end of December 2023 and passed final inspection in mid-April 2024, about 15 weeks start to finish. The plans were drawn by Whalen Architecture.

​

What we built

  • First floor: a full bathroom with laundry, and a home office

  • Second floor: two bedrooms

  • Exterior: board-and-batten siding, Andersen windows and a covered entry with stairs to the yard

​

See more home additions or more of our work in Beacon.